Here you’ll find the latest information regarding the Metropolitan Natural Gas Reliability Project. Make sure to use the Contact Us page and sign up to get these updates directly to your email inbox.

Last week our construction team continued work along Moore Street, Manhattan Avenue, and Montrose Avenue. This week our crews will be working on Manhattan Avenue, Montrose Avenue, Graham Avenue, Meserole Street, and Waterbury Street. Click here for an overview of…

Read Post

This week our construction team continued work along Moore Street, Manhattan Avenue, and Montrose Avenue. We are pleased to report that temporary restoration of the sidewalk is complete on Moore Street between Bushwick Avenue and Humboldt Street. Next week our…

Read Post

This week our construction team continued work along Moore Street, Manhattan Avenue, and Montrose Avenue. Temporary restoration is ongoing on Moore Street between Bushwick Avenue and Humboldt Street. Next week our crews will be working on Moore Street, Manhattan Avenue,…

Read Post

This week our construction team continued work along Moore Street, Manhattan Avenue, and Montrose Avenue. Temporary restoration is ongoing on Moore Street between Bushwick Avenue and Humboldt Street, and on Montrose Avenue between Lorimer Street and Manhattan Avenue. Click here…

Read Post

This week our construction team continued work along Moore Street, Manhattan Avenue, and Montrose Avenue. We are pleased to note that we have started temporary restoration on Moore Street between Bushwick Avenue and Humboldt Street, and on Montrose Avenue between…

Read Post

This week our construction team continued work along Bushwick Avenue, Montrose Avenue, Manhattan Avenue, and Moore Street. We are pleased to note that we have completed temporary restoration on Bushwick Avenue up to Moore Street. Please note that due to…

Read Post

This week our construction team continued work along Bushwick Avenue, Montrose Avenue, Manhattan Avenue, and Moore Street. Please note that due to changes in construction sequence, our team will be returning to Flushing Avenue (between Central Avenue and Evergreen Avenue)…

Read Post

This week our construction team continues work along Bushwick Avenue, Montrose Avenue, and Moore Street. We are pleased to note that we have completed temporary road restoration on Bushwick Avenue up to Varet Street. Please note that due to changes…

Read Post

This week our construction team continued work along Bushwick Avenue, Montrose Avenue, and Moore Street. We are pleased to note that we have completed temporary road restoration on Bushwick Avenue up to Varet Street. Click here for an overview of…

Read Post

This week our construction team continued work along Flushing Avenue, Bushwick Avenue, and Montrose Avenue. Our team also began work on Moore Street. We are pleased to note that we have completed temporary road restoration on Flushing Avenue up to…

Read Post

This week our construction team continued work along Flushing Avenue and Bushwick Avenue, and began work on Montrose Avenue. We are pleased to note that we have completed temporary road restoration on Flushing Avenue up to Stanwix Street. Click here…

Read Post

Happy New Year! This week our construction team resumed work on Flushing Avenue and Bushwick Avenue after the holiday break. Click here for an overview of the route for this phase of the project. As always, our outreach team continues…