Our construction team has continued progressing along Thomas S. Boyland Street over the last week. Trenching has reached Bainbridge Street, and should be approaching Decatur Street next week. We are pleased to note we have completed backfilling along Hull Street and permanent restoration of the sidewalk on Herkimer Street. Our outreach team has continued discussing upcoming construction schedules with residents and other local partners.

*Over the next week, neighbors can expect to see:

  • Continued work along Thomas S. Boyland Street between Hull Street and Decatur Street, including trenching, gas main installation, and welding.
  • Expect changes in traffic patterns along Saratoga Avenue, and Thomas S. Boyland Street between Fulton Street and Decatur Street. We will have flaggers on site to redirect traffic as necessary.

As always, feel free to reach out by emailing us at BrooklynMetro@NationalGridGasProjectsNY.com, or calling our project hotline (718-337-8138). Also, please make sure to use the signup box below to receive these updates directly to your email inbox.

*Please note, due to the complexities of outdoor construction, schedule is subject to change.