Here you’ll find the latest information regarding the Metropolitan Natural Gas Reliability Project. Make sure to use the Contact Us page and sign up to get these updates directly to your email inbox.
Last week our construction team continued work on Decatur Street between Broadway and Evergreen Avenue. This week the team will be engaging mainly in preparatory work offsite. The outreach team will continue to discuss upcoming construction schedules with residents and…
Last week our construction team continued work on Decatur Street between Broadway and Evergreen Avenue. We are pleased to note we finished backfilling in the intersection of Decatur Street and Bushwick Avenue. The outreach team will continue to discuss upcoming…
Last week our construction team continued work on Decatur Street between Broadway and Evergreen Avenue. The outreach team will continue to discuss upcoming construction schedules with residents and other local partners. *Over the next week, neighbors can expect to see:…
Last week our construction team continued work on Decatur Street between Broadway and Evergreen Avenue. The outreach team will continue to discuss upcoming construction schedules with residents and other local partners. *Over the next week, neighbors can expect to see:…
Last week our construction team continued work on Decatur Street between Broadway and Evergreen Avenue. The outreach team will continue to discuss upcoming construction schedules with residents and other local partners. *Over the next week, neighbors can expect to see:…
Last week our construction team continued work on Decatur Street, beginning backfilling and temporary restoration between Broadway and Bushwick Avenue. The outreach team will continue to discuss upcoming construction schedules with residents and other local partners. *Over the next week,…
Last week our construction team continued work on Decatur Street. We are pleased to note we finished backfilling on Decatur Street between Thomas S. Boyland Street and Broadway. The outreach team will continue to discuss upcoming construction schedules with residents…
Last week our construction team has continued work on Decatur Street. We are currently backfilling on Decatur Street between Thomas S. Boyland Street and Broadway and installing the gas main between Broadway and Bushwick Avenue. The outreach team will continue…
Over the past week, our construction team has continued work on Thomas S. Boyland, Street completing backfilling and temporary repaving up to Decatur Street. We are working on Decatur Street and will continue to work there for the next few…
Our construction team has completed backfilling and temporary repaving on Thomas S. Boyland Street up to Bainbridge Street. We are working along Decatur Street and will continue to work there for the next few weeks. Our outreach team has continued discussing upcoming construction schedules with residents and other local partners. *Over…
This week, work has continued up Thomas S. Boyland Street at a steady pace. Our construction team has turned the corner onto Decatur Street and is approaching Broadway. We are pleased to note we have completed backfilling along Thomas S….
Our construction team has continued progressing along Thomas S. Boyland Street over the last week. Trenching has reached Bainbridge Street, and should be approaching Decatur Street next week. We are pleased to note we have completed backfilling along Hull Street…