Updates

We are happy to report that the newly installed gas main has been put into limited service. Over the coming weeks our crews will be monitoring the new gas main as we transition to full service. Our crews may be…

Read More

This week our crews will be backfilling on Seneca Place and on Babylon Turnpike. There may be isolated work on Commonwealth Avenue and on Oakwood Avenue. On Thursday and Friday, we are scheduled to odorize the new gas main. Odorization…

Read More

Happy Thanksgiving week! In observance of the holiday weekend our crews will not be working on Thursday, November 28th or Friday, November 29th. This week our crews will continue work on Babylon Turnpike, Commonwealth Avenue, Oakwood Avenue, and Seneca Place….

Read More

We are pleased to announce the successful completion of the quality assurance testing phase of the Merrick Reinforcement Project. Our crews will remove the testing equipment on Babylon Turnpike and on Seneca Place by midweek. Thank you for your continued…

Read More

Happy Veterans Day! This week our contractors will continue the quality assurance testing phase of the Merrick Reinforcement Project. Our crews will be working full time to complete required testing. Testing activity will take place on Babylon Turnpike and on…

Read More

This week our contractors will begin the quality assurance testing phase of the Merrick Reinforcement Project. Our crews will be working full time to complete required testing. Testing activity will take place on Babylon Turnpike and on Seneca Place. While…

Read More

Due to unforeseen delays, our contractors will begin final restoration of the roadway on Tuesday, October 29. Contractors will work to mill and pave as much of the project route as possible prior to the Halloween holiday. Again, we greatly appreciate your…

Read More

This week our crews will continue working on Commonwealth Avenue, Babylon Turnpike, and Seneca Place. Additionally, we’re happy to report that backfilling has been substantially completed on Commonwealth Avenue. However, the daytime road closure remains in effect on Commonwealth Avenue…

Read More

This week our crews will continue working on Commonwealth Avenue, Babylon Turnpike, and Seneca Place. Traffic around the work zones will be directed by flaggers as needed. Drivers traveling past the work zones should expect delays and plan accordingly. We…

Read More

This week our crews will continue working on Commonwealth Avenue, Babylon Turnpike, and Seneca Place. Traffic around the work zones will be directed by flaggers as needed. Drivers traveling past the work zones should expect delays and plan accordingly. We…

Read More

This week our crews will continue working on Commonwealth Avenue and on Babylon Turnpike. We are pleased to note that backfilling on Commonwealth Avenue has been completed up to the Madison Street intersection. In addition to our work on Commonwealth…

Read More

This week our work zone will be expanding as we begin work on Babylon Turnpike. In addition to our work on Babylon Turnpike, our crews will be continuing work on Commonwealth Avenue, and returning to Seneca Place to finish work on…

Read More